2022 Bids

Bids require Adobe Acrobat Reader

It is the contractor's responsibility to make certain they have received any/all addenda relating to their bid prior to the bid opening date.

If you are downloading a bid, we strongly encourage you to notify the RMLD's Purchasing Department and provide us with your Company Name, Address, Phone & Fax # and which bid number you downloaded.

**An RFQ does not have a formal opening. Quotes are due back by deadline listed.

For a copy of an Invitation for Bid (IFB), an Invitation for Proposal (IFP) or a Request for Proposals (RFPs), please contact Paula O'Leary at poleary@rmld.com or Maureen Sullivan at msullivan@rmld.com .

If you leave a voice mail, please include all contact information including your e-mail address.

Thank you.

Title Number Start Datesort descending End Date Status
Solid Dielectric Motor Operated Padmounted Switchgear IFP 2022-08 01/26/2022 - 12:00pm 02/16/2022 - 11:00am Canceled
Trouble Truck with Trade-In IFP 2022-01 02/02/2022 - 12:00pm 02/23/2022 - 11:00am Awarded
Home Energy Assessment Program IFB 2022-04 02/02/2022 - 12:00pm 02/23/2022 - 11:00am Awarded
Pole Mounted Transformers IFP 2022-09 02/09/2022 - 12:00pm 03/16/2022 - 11:00am Awarded
Pad Mounted Transformers IFP 2022-10 02/09/2022 - 12:00pm 03/16/2022 - 11:00am Awarded
RMLD Substation 4 Transformer Testing and Repairs IFP 2022-11 03/23/2022 - 12:00pm 04/13/2022 - 11:00am Canceled
Technical and Project Leader Services for RMLD AM/MDM Project RFQu 2022-17 03/29/2022 - 10:30am 04/19/2022 - 4:30pm Pending
Electric Utility Excavation Services IFB 2022-18 04/13/2022 - 12:00pm 05/04/2022 - 11:00am Awarded
Cloud PBX Telephone System 2022 IFB 2022-12 04/13/2022 - 12:00pm 05/04/2022 - 11:00am Canceled
Low Voltage Cabling Design, Installation, and Restoration RFQ 2022-22 05/11/2022 - 1:00pm 06/01/2022 - 12:00pm Canceled
RMLD Substation 4 Transformer Testing and Repairs IFB 2022-24 06/01/2022 - 12:30pm 06/22/2022 - 11:00am Canceled
350 MCM CU 35kV EPR Underground Cable IFP 2022-27 06/15/2022 - 12:00pm 07/06/2022 - 11:00am Awarded
750 MCM 15kV Power Cable IFP 2022-28 06/15/2022 - 12:00pm 07/06/2022 - 11:00am Awarded
Technology Upgrades in Six (6) RMLD Conference Rooms RFQ 2022-13 06/22/2022 - 3:00pm 07/13/2022 - 12:00pm Awarded
RMLD Parking Lot Repairs RFQ 2022-35 08/17/2022 - 12:15pm 09/07/2022 - 12:00pm Awarded
Substation Transformer Testing and Repairs IFB 2022-39 09/07/2022 - 3:00pm 09/29/2022 - 11:00am Canceled